Hedrick Middle School

Estimated Construction Dates: June 2009-Fall 2009
Last Updated on 2.24.09
View the new Progress Videos Page

PROJECT SUMMARY:                                                                                        © David Gibb Photography

Hedrick Middle school was built in 1955 and has 41 classrooms on its 11 acre campus.  It will have heating, ventilation and air conditioning upgrades, security upgrades, new flooring and piping repairs.
The Medford School District advertises requests for proposals (RFPs) at http://www.medford.k12.or.us/RFP.asp?SectionID=140

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: MSD www.medford.k12.or.us
 Architect: District Design www.medford.k12.or.us
 Contractor: TBA Will bid spring 2009

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-1/31/09
$1,600,000 $431,621
Click here to see the monthly expenditures report.

Project Description & Status :
Project: Status
Heating & Ventilation Upgrades Summer 2009
Security Upgrades Complete
New flooring Summer 2009
New roof Summer 2008
Pipe repairs Summer 2009
New gym bleachers Complete


PROJECT PHOTOS:
 

New gym bleachers

 

 